Kutaisi International Airport's New Passenger Terminal Facade and Internal Partition Arrangement Completed

The main works on the facade of the new Kutaisi International Airport terminal and the arrangement of internal partitions have been completed, as well as roof installation. 

At this stage, the roof is being greened and an open porch arranged. 

In parallel, the third phase of construction works is underway. That means arranging engineering-communications. After that, the terminal will be equipped with special equipment, heating and cooling system.

Internal repairs and outdoor landscaping will begin soon.

After the construction of the new passenger terminal, the airport will have 7 exits (the so-called Gate) and will be able to carry 1,200 passengers per hour without interruption. The airport's capacity will increase by 4 times.