Home / Economy / TELASI Company Installs Three Reverse Meters

TELASI Company Installs Three Reverse Meters

TELASI company has already installed three reveres meters. Under amendments adopted in 2015, all subscribers are able to generate electricity themselves and sell excessive volume. Micropower electricity stations  are required to this end (solar panels of about 110 kw/h, wind generators and micro HPPs).

According to changes to GNERC resolution on Regulations for Electricity Supply and Consumption, a subscriber should apply to corresponding distribution licensee  for connecting the micropower electricity station into the network.

Applications should be submitted to  TELASI central office, due to requirements determined by the regulatory commission. Based on the type of applications, licenses will be issued and meters will be installed within 10-20 days.